GUJARAT EARTHQUAKE : BULLETIN ON RELIEF
ARRANGEMENTS BY INDIAN RAILWAYS
- The earthquake that occurred on 26.01.2001 has caused severe devastation
in Gujarat. The track on Viramgam – Gandhidham BG section, Navlakhi –
Dahinsara BG section and Palanpur – Gandhidham MG section has suffered
extensive damage. Communication has been disrupted on these sections. There
have been damages to Railway station buildings (100), bridges(36),cabins(15)
and staff quarters(350). Railways have launched relief operations on a war
footing.
Restoration efforts are being affected by reports of fresh
tremors of lesser intensity occurring in the area.On the Viramgam – Gandhidham BG route, the line has been
certified upto Samakhiali and Control communication is available upto
Samakhiali. There is no DOT communication with Gandhidham. Train service is up
to Maliya Miyana Jn. only.The broad guage line upto Gandhidham has been
restored for rail trafficat 13 hrs today.
On the Palanpur – Gandhidham MG section, the line has been
certified upto Kidiyanagar and Control communication is available up to
Kidiyanagar. Train service is up to Radhanpur only. CE/HQs has reported that the track between Navlakhi and
Dahinsara is sunk by 1 to 3 metreDRM/ BRC with branch officers, CE/works,
CEE/WR, CBE/WR are
at site along with other engineers are engaged in the activity of
restoration.
- Special Trains
:
The following special trains have been operated for carrying
relatives of quake victims and NGOs free of cost. Trains have also been operated
to clear victims and their families from the affected areas. Wide publicity has
been given through press and media about the running of special trains.
|
From |
Date of Departure& composition |
Destination |
Route and stoppages |
Status |
|
Chennai Dep. 1605 hours |
27.01.2001 14 coaches |
Ahmedabad/ Dharangadra |
Gudur,Bitragunta,Vijaywada,Balharshah,Wardha,Badnera,
Bhusaval,Jalgaon,Nandurbar,Surat,Vadodara |
Reached Ahmedabad 0700 Hrs 29/01/2001 |
|
Bangalore dep. 1600 hours |
27.01.20018 Coaches |
Ahmedabad/ Dharangadra |
Dharmavaram,Guntakal,Gooty,Raichur,Wadi,Solapur,Daund,
Manmad,Jalgaon,Vadodara |
Reached Ahmedabad at0525Hrs 29/01/2001 |
|
Howrah dep. 1700 hours |
27.01.200118 coaches |
Ahmedabad/ Dharangadra |
Kharagpur,Tata,Chakradharpur,Rourkela,Jharsugda,Balaspur,
Durg,Nagpur,Wardha,Badnera,Akola,Bhusaval,Jalgaon,Vadodara |
Passed Vadodara 09/30 hrs on date |
|
Mumbai dep. 1800 hours |
27.01.200118 Coaches |
Ahmedabad/ Dharangadra |
Valsad,Navasari,Surat,Vadodara,Ahmedabad,Varamgam,
Dhrangadhara |
Reached Dharangadra at 8.55 hrs on
28.01.01 |
|
Delhi dep. 1715 hours |
27.01.200113 coaches |
Ahmedabad/ Dharangadra |
Rewari,Jaipur,Ajmer,Palanpur,Mehesana |
Reached Ahmedabad at 1615 hrs on 28.01.2001 2
|
|
Ahmedabad dep. 2310 hours |
27.01.200114 Coaches |
Mumbai |
Surat,Bharuch, |
Reached Mumbai at 10.42 hrs on
28.01.2001 |
|
Delhi dep.1700 hrs. |
28.01.2001
14 coaches |
Ahmedabad |
|
Passed Palanpur at 0910hrs on date |
|
Mumbai dep1700 hrs |
28.01.2001
15 coaches |
Dharangadra |
|
Passed SADLA 0810 hrs. on date |
|
Howrah dep. 1700 hrs |
28.01.2001
13 coaches |
Ahmedabad |
|
Passed Durg at08/20 hrs |
|
Chennai dep. 1700 hrs |
28.01.2001
12 coaches |
Ahmedabad |
|
Passed BALLARSHA--H at 11/15 hrs on date |
|
Bangalore dep.1800 hrs. |
28.01.2001
11 coaches |
Ahmedabad |
|
Passed DAUND at 12/20 Hrs hrs on date |
|
Ahmedabad
Dep.2320 hrs. |
28.01.2001
13 coaches |
Delhi |
|
Passed SOD at 0820 hrs. on date |
|
Ahmedabad
Dep. 2310 hrs |
28.01.2001
16 coaches |
Mumbai |
|
Reached Mumbai at07/55 hrs on date |
|
Bhopal
Dep.1935 hrs |
28.1.2001 |
Ahmedabad |
|
Reached Ahmedabad at 10.00 Hrs. on
date |
One Military special containing 11 coaches left Ambala 1840
hours (27.01.2001) for Ahmedabad carrying tentage. This train will carry quake
affected armed forces families back to JRC on NR. The train reached Ahmedabad at
0200 hrs on 29.01.2001.
In return direction a special train has been ordered at 23.00
Hrs on date from Ahmedabad to Mumbai.A special train has also been ordered from
Mumbai to Ahmedabad on date at 1700 hrs
- Emergency Cells
:
The following emergency cells are operating round-the-clock
manned by officers:
|
Office |
Telephone No.s |
|
Railway Board, New Delhi |
011- 3388503, 011- 3388230 |
|
Western Railway, Mumbai |
022 -2017420 |
|
Ahmedabad |
079 - 2111413 |
|
Ajmer |
0145 - 421048 |
|
Rajkot |
0281 - 454063 |
|
Vadodara |
0265 - 641244 |
- Medical Relief trains
:
Three Medical relief trains were run from
Ahmedabad, Udna and
Palanpur with a team of doctors and medical equipment.
|
Ahmedabad to Dharangadra |
1 ARME + 2GS dep. 1525 -- 6 doctors |
Arrived DHG at 1850 hours on 27.01.2001 |
|
Udna to Dharangadra |
Dep. 1850 2 GS – 2 doctors |
Reached DHG at 0300 hours 28.01.2001 |
|
Palanpur to Radhanpur |
5 GS dep. 1925 – 1 doctor ; 3 by road |
Arrived Radhanpur at 0120 hours on
28.01.2001 |
Movement of materials and men:
- Bull-dozer special (A-class ODC) consisting of 4 BRH(flat wagons)
loads with dozers left Bhilai at 0315 hours on 28.01.2001. Passed Bhusawal
1130 hrs. on date.
- One rake of GI Strips was on the point of departure ( TE on) with 8
BOX + 5 BRH. This train will pickup 11 BOX loaded from Tumsar Road. The
train passed Bhusawal 1355 hrs. on date.
- First labour special of 225 men reached Maliya at 1340 hours on
27.01.2001.
- One water special left Ahmedabad at 0500 hrs on date for Ghandhi Dham
andd Nalia.
- One water special under loading at Sabarmati for Nalia and Ghandhi
Dham.
- Two Ballast special reached Indiranagar on 28.1.2001
- 4 buses of labour 124 men sent from Palanpur
- Relief material consisting of 700kg atta, 500 kg Potatoes, 200kg
Onion, 200 blankets, 1000 water pouches sent by truck ex-Ahmedabad at 1235
on 27.01.2001. One water tanker moved by 111 Passenger.
- Relief material consisting of 70 blankets, 80 kg Potatoes, Onions,
Atta, Cooking oil tents etc. sent by truck ex-Abu Road on 27.01.2001.
- One team of Doctors under supervision of CMS/Ajmer left for site
(between Samakhiali and Gandhidham by road)
- A material train ex-Palanpur with 600 cribs and 100 sleepers and all
engineering relief material reached Adheser at 10.3 hrs on 28.01.2001
- 6 rakes of ballast have been stationed as under-
14 BKH at Sabarmati 1920 hrs 28.1.2001
27 BKH at Godhra 0410 hrs 29.1.2001
22 BKH at Nadiad 03.30 hrs 29.1.2001
23 BKH at Viramgram 03.10 hrs 29.1.2001
10 BKH at Surat 01.55 hrs 29.1.2001
39 BKH in B/section between Maliya and
Samakhiali
- ( BG ) 3700 sleepers and 2030 cc cribs have been mobilised at
Sabarmati
- ( MG ) 600 cc cribs and 275 sleepers have been mobilised at Aesar
- Trains Cancelled on 29.01.2001:
- 4311/12 BE- Gandhidham Express
- 6335/36 Gandhidham – NCJ Express between Ahmedabad and Gandhidham
- 9031/32 Kutch Express between Gandhidham and DHG
- 9601/02 BDTS- Gandhidham Exp. Between BRC and Gandhidham
- 111/112 Passenger between Halvad and Gandhidham
- 2 pairs of MG passengers between Kidiyanagar and Gandhidham
- Passenger services between Dahinsara and Navlakhi
|